Proposition approval
would fix leaking roofs, leaking boilers, sagging
ceilings and more
A leaking, asbestos-lined
boiler. Broken front doors. A
leaking roof that has forced students to dance around
buckets while lining up for lunch. A
1,000-gallon, electric-fired hot water heater that
“burns” cash. A falling
ceiling. Even an odoriferous
and potentially unsanitary leech field.
These are just some of the
conditions that would be fixed through repair or
replacement if RCS district voters approve two
propositions going before them on October 9. Residents
will head to the voting booths in the High School
gymnasium from 7 a.m. to 9 p.m. that day to vote on
three propositions:
-
Proposition 1 seeks
approval to spend $2,353,243 to improve the safety
and energy efficiency of the district’s four
schools. The projects would receive nearly 100
percent in state aid through a one-time state
program, called EXCEL. The grant program covers the
cost of capital projects traditionally shouldered by
taxpayers, leaving only interest costs for RCS
taxpayers to cover.
Those projected cost, said Interim Business
Administrator Gene Grasso, would average less than $10,000 a year for 15 years.
-
Proposition 2 seeks
voter approval to spend $390,000 to replace the
leaky roof of the bus garage and install a more
energy efficient boiler and a fuel monitoring
device. The work is eligible for standard 70 percent
state aid
that would reduce
the projected cost to taxpayers of the project to
$10,327 a year.
-
Proposition 3 seeks a
voter recommendation on candidates for the ninth
seat on the Board of Education.
Energy
efficiency in gas
Perhaps one of the most
cost-efficient projects proposed is the piping of
natural gas to allow its use in the middle school.
The building is currently
the only one in the district without natural gas and
relies solely on the more costly energy source of
electricity to provide heat and hot water to the food
preparation areas, as well as faculty, staff and
students.
The $110,000 cost to
install natural gas service to the building would allow
the district to replace the three-decade-old
electric-fired hot water heater heating system with a
natural gas fired system, as well as a separate electric
hot water heater for the kitchen.
Additionally, the new
natural gas service would allow the district to replace
out-dated electric air conditioning/heating units for
the library and cafeteria, thereby providing additional
savings to taxpayers, said interim facilities director
Jeff Clemens.
In the high school, work
would include the $288,000 replacement of the leaking
roof over the cafeteria wing that last year led to the
placement of buckets and garbage cans in the hallway
outside the cafeteria. This summer, new leaks appeared
in the food preparation area and had to be addressed
immediately – through a temporary fix – in order to
meet state health department requirements.
Other projects include:
-
Replacing faulty
thermal windows at a cost of $414,000 with energy
efficient models that reduce heating costs and
provide a warmer classroom environment in the
winter.
-
Replacement of one of
the two leech fields which is failing, leading to
over-saturated, potentially unsanitary and at times
odiferous ground.
-
Replacement of door
handles and locks which do not meet Americans with
Disabilities Act (ADA) guidelines
-
Replacement of main
entrance doors which fail and could pose a safety
problem in an emergency and reconstruction of the
gymnasium ceiling which is sagging in areas.
-
Expansion of the
loading dock which is too small to fully accommodate
new trucks bringing supplies to the school.
It’s
elementary
In A.W. Becker and Pieter
B. Coeymans elementary schools, approval of proposition
1 would mean the replacement of decades-old
asbestos-lined hot water heaters, which at A.W.B, is
leaking. More energy efficient piping would be installed
in the boiler rooms as well. Nearly $250,000 would be
spent at each school.
Unique
opportunity
State building aid already
pays for 70 percent of the cost of most RCS construction
work. In
2006, the state
Legislature created a new short-term form of building
aid called EXCEL (Expanding Children’s Education and
Learning) that is meant to cover local taxpayer costs.
Legislators agreed to send $1.8 billion of EXCEL aid to
the New York City Schools to begin settling the
long-standing Campaign for Fiscal Equity court case. At
the same time they set aside $800 million in EXCEL aid
to be shared by the 700-some public school districts
outside of New York City.
Because of this unique
opportunity, RCS is able to propose a $2.35 million
capital project that would cost taxpayers only
approximately $15,000 a year for 15 years.
Didn’t
we just complete a capital project?
The district completed in
2005 a capital project that upgraded many of the
districts’ facilities and provided expanded facilities
students and the community.
However, as a result of
unforeseen material price increases, construction issues
and the like, the district was forced to cut some of the
projects from that Capital Project as work advanced.
When this unique
opportunity to access additional state aid to complete
the much needed work came about as a result of state
legislation, the Board of Education decided to place the
project before voters.
Proposition 2 – the bus garage
“When it rains the water
runs down the wall through the drop ceiling and pools on
the floor near my desk,” said Transportation Director
Janice Prior, describing the need to replace the
decades-old roof at the bus garage.
Roof replacement of the
bus garage is the major aspect of proposition 2 on the
October 9 ballot.
Other work called for in
the project includes installation of a fuel-monitoring
device and reconstruction of the
fuel island, as well as replacement of the
building’s antiquated boiler.
Unlike proposition 1, the
bus garage work is not eligible for state EXCEL aid,
though it would still be eligible for the standard state
building aid, which covers 70 percent of the cost. That
would reduce the total cost to taxpayers of the project
to $10,327 a year.
“What is being proposed
would solve some major problems RCS has been dealing
with at little cost – approximately $25,000
combined
– annually to district taxpayers,” said Superintendent
Vicki Wright. “For comparisons sake, we just spent
$14,000 to provide a short-term fix to the leaky
cafeteria wing.”
At the same time, approval
of these propositions would provide a savings to
taxpayers not only in terms of reducing maintenance
costs, but also reducing energy costs in all four school
buildings, as well as the bus garage.