Please be advised that milling and paving at RCS Middle School and RCS High School is anticipated to begin on Friday, August 8, 2025, through Friday, August 24. This work will be completed in phases, and the 9W campus entrance will be closed during parts of the project.
Please refer to the project schedule and accompanying maps below for details on campus access and available parking during each phase. Note: All outdoor work is weather-dependent. Please check the District website and communication platforms regularly for updates. Active construction areas will be clearly marked and protected. We ask that all campus visitors use caution and follow posted traffic and parking instructions during this time.
Thursday, August 14 and Friday, August 15
Milling and paving (first course) of Stadium and Aquatic Center entrance and parking lot, High School visitor and student parking lots, and bus loop. The 9W campus entrance will be open. Areas marked in red will be closed.
Tuesday, August 19:
Paving (top course) of the bus loop and gym entrance to the Middle School. The 9W campus entrance will be open. Areas marked in red will be closed.
Wednesday, August 20 through August 24th:
Paving (top course).
The following areas will be closed:
The 9W campus entrance
Middle School Parking Lot
Bus Loop
Entrance to the Stadium and Aquatic Center
High School student parking lot
High School visitor parking lot
Please use Rt. 101 entrance for access to the campus. Parking lot available during this stage is marked in orange. Please see the map below for campus access and parking. Areas marked in red will be closed.
Thank you for your patience and support as we continue to enhance our facilities for the entire RCS community!